2019-U3a Wastewater Treatment Plant design is in process with anticipated completion 2023, 2021-U1 WTP High-Pressure Pump VFD is in process

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant design is in process with anticipated completion 2023, 2021-U1 WTP High-Pressure Pump VFD is in process, and 2021-U2 WTP Replacement of Valves received no responses to the initial bid

April 4, 2022 · official recordDeb report / update

The official record attributes the report or update to Stuart. The item concerns utilities and records activity described as utilities.

Official source: Mason City Council · council packet · page 27

Official source

Each historical entry links back to the reviewed official record used to support the description above.

April 4, 2022 · official recordPage 27

Mason City Council

Record details: Mason City Council · council packet · page 27.

View official source ↗
2019-U3a Wastewater Treatment Plant design is in process with anticipated completion 2023, 2021-U1 WTP High-Pressure Pump VFD is in process | Deb Tracker | Townstoria