The official record attributes the report or update to Stuart. The item concerns utilities and records activity described as utilities.
Official source: Mason City Council · council packet · page 29
Historical record
Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.
The official record attributes the report or update to Stuart. The item concerns utilities and records activity described as utilities.
Official source: Mason City Council · council packet · page 29
Each historical entry links back to the reviewed official record used to support the description above.
Record details: Mason City Council · council packet · page 29.