A source-backed timeline of City of Mason records explicitly connected to Project 2018 U32 in Civic Core.
Deb Tracker groups records here only when the audited record explicitly matches this named subject. The underlying civic events remain separate, and every timeline entry links back to its source-backed record page.
Reported that 2017-U8 Replace PLCs on 3 Wells and 2017-U23 Well No. 6 Rebuild have anticipated start dates in Spring of 2021, 2017-U25 Gutters for Water Treatment Plant was completed in April, 2018-U32 South Water Tower Repair is preparing documents for bid advertising, 2019-U1 Wastewater Treatment Plant - Design staff is drafting Request for Proposal for work
Reported that 2018-U32 South Water Tower Repair is preparing documents for bid advertising.
The report stated that 2018-U32 South Water Tower Repair was in progress and expected to be completed by October.
Reported that 2018-U32 South Water Tower Repair was completed and the tower is back in service in October.