June 19, 2023 · official recordActor not established1 official source reference
Status: executed
City Manager role: unclear
Official record
Project 2017-B5b Building: Library Phase 1, Part 1 had an executed contract for only the grant portion and entrances and bathrooms of the project, with finalizing the contract for the remainder anticipated in July.
Status: executed
City Manager role: unclear
1 official source reference across 1 official document.
Project 2017-B5b Building: Library Phase 1, Part 1 had an executed contract for only the grant portion and entrances and bathrooms of the project, with finalizing the contract for the remainder anticipated in July.
View official source ↗