Status: planned
City Manager role: reported update
Official record
The update listed the PLC replacements on 3 Wells with an anticipated start date in Spring of 2021, Well No. 6 Rebuild in progress, South Water Tower Repair with anticipated work to begin fall 2021, Well No. 4 Rebuild in progress, Wastewater Treatment Plant design drafting a Request for Proposal, and Wastewater Solids System completed in March.
Status: planned
City Manager role: reported update
1 official source reference across 1 official document.
The update listed the PLC replacements on 3 Wells with an anticipated start date in Spring of 2021, Well No. 6 Rebuild in progress, South Water Tower Repair with anticipated work to begin fall 2021, Well No. 4 Rebuild in progress, Wastewater Treatment Plant design drafting a Request for Proposal, and Wastewater Solids System completed in March.
View official source ↗