October 21, 2019 · official recordcontractor1 official source reference
Status: submitted
City Manager role: outside information relayed
Official record
for Kerns Road to Cedar Street to Howell Rd./Hayhoe Riverwalk Trail Extension the contractor is in place, plans and a permit request were submitted to ICRD for the Howell Road crossing, and the project is on hold until Spring 2020.
Status: submitted
City Manager role: outside information relayed
1 official source reference across 1 official document.
for Kerns Road to Cedar Street to Howell Rd./Hayhoe Riverwalk Trail Extension the contractor is in place, plans and a permit request were submitted to ICRD for the Howell Road crossing, and the project is on hold until Spring 2020.