a high-pressure pump VFD anticipated in December 2023, replacement of valves placed on hold, and a sanitized sewer, storm water

Reported project status updates for streets, sidewalks, signals, and utilities, including completed projects, a signal at E. Maple and S. Jefferson in flashing red with temporary stop signs deployed, wastewater treatment plant design in process, a high-pressure pump VFD anticipated in December 2023, replacement of valves placed on hold, and a sanitized sewer, storm water, and water distribution project expected to start in June.

June 6, 2022 · official recordActor not established1 official source reference

Status: delayed

City Manager role: reported update

Sources and supporting records

1 official source reference across 1 official document.

June 6, 2022 · official recordPage 47

Mason City Council

Reported project status updates for streets, sidewalks, signals, and utilities, including completed projects, a signal at E. Maple and S. Jefferson in flashing red with temporary stop signs deployed, wastewater treatment plant design in process, a high-pressure pump VFD anticipated in December 2023, replacement of valves placed on hold, and a sanitized sewer, storm water, and water distribution project expected to start in June.