August 2, 2021 · official recordActor not established1 official source reference
Status: completed
City Manager role: reported update
Official record
Provided a status update that railroad work for the Jefferson St pedestrian crossing was complete and concrete/asphalt work was scheduled for October.
Status: completed
City Manager role: reported update
1 official source reference across 1 official document.
Provided a status update that railroad work for the Jefferson St pedestrian crossing was complete and concrete/asphalt work was scheduled for October.