Staff reported that pre-construction was held for the Columbia Bridge Non-Motorized Connect project, work is planned to occur 10/2-10/20, property owners were notified, and a grant amendment request has been submitted to Ingham County.
Status: in progress
City Manager role: reported update
1 official source reference across 1 official document.
Staff reported that pre-construction was held for the Columbia Bridge Non-Motorized Connect project, work is planned to occur 10/2-10/20, property owners were notified, and a grant amendment request has been submitted to Ingham County.