December 6, 2021 · official recordActor not established1 official source reference
Status: in progress
City Manager role: reported update
Official record
The report gave a total estimated project cost of $835,000, committed funds of $726,320 including $275,000 from City of Mason, recent funding commitments, and that staff is working with CADL to apply for Patronicity.
Status: in progress
City Manager role: reported update
1 official source reference across 1 official document.
The report gave a total estimated project cost of $835,000, committed funds of $726,320 including $275,000 from City of Mason, recent funding commitments, and that staff is working with CADL to apply for Patronicity.