← Back to Deb Tracker

Official record

2017-U25 Gutters for Water Treatment Plant was completed in April

Reported that 2017-U8 Replace PLCs on 3 Wells and 2017-U23 Well No. 6 Rebuild have anticipated start dates in Spring of 2021, 2017-U25 Gutters for Water Treatment Plant was completed in April, 2018-U32 South Water Tower Repair is preparing documents for bid advertising, 2019-U1 Wastewater Treatment Plant - Design staff is drafting Request for Proposal for work

Sources and supporting records

2 official source references across 2 official documents.

May 17, 2021 · official recordPage 54

Mason City Council

Reported that 2017-U8 Replace PLCs on 3 Wells and 2017-U23 Well No. 6 Rebuild have anticipated start dates in Spring of 2021, 2017-U25 Gutters for Water Treatment Plant was completed in April, 2018-U32 South Water Tower Repair is preparing documents for bid advertising, 2019-U1 Wastewater Treatment Plant - Design staff is drafting Request for Proposal for work

View official source ↗
May 3, 2021 · official recordPage 144

Mason City Council

Reported that 2017-U8 Replace PLCs on 3 Wells and 2017-U23 Well No. 6 Rebuild have anticipated start dates in Spring of 2021, 2017-U25 Gutters for Water Treatment Plant was completed in April, 2018-U32 South Water Tower Repair is preparing documents for bid advertising, 2019-U1 Wastewater Treatment Plant - Design staff is drafting Request for Proposal for work