April 15, 2019 · official recordcontractor1 official source reference
Status: started
City Manager role: outside information relayed
Official record
The report said MDOT had started the signal upgrade project at the intersection of Ash and Cedar (M-36), with the contractor completing installation of the signal foundations and the remaining signal and sidewalk work to occur later.
Status: started
City Manager role: outside information relayed
1 official source reference across 1 official document.
The report said MDOT had started the signal upgrade project at the intersection of Ash and Cedar (M-36), with the contractor completing installation of the signal foundations and the remaining signal and sidewalk work to occur later.
View official source ↗