Reported that project 2017-B5b Building: Library Phase 1, Part 1 executed contract for only the grant portion of the project covering entrances and bathrooms.
Status: executed
City Manager role: unclear
1 official source reference across 1 official document.
Reported that project 2017-B5b Building: Library Phase 1, Part 1 executed contract for only the grant portion of the project covering entrances and bathrooms.