March 30, 2022 · official recordActor not established1 official source reference
Status: delayed
City Manager role: reported update
Official record
Reported that Fire Rehab 815 Replacement is anticipated 4th quarter of FY 21-22, City Hall Phase I Design and Security has security complete but work space evaluation delayed due to staff capacity, DPW design concepts are being finalized, Library Phase 1 Part 1 had no bids again on March 30
Status: delayed
City Manager role: reported update
1 official source reference across 1 official document.
Reported that Fire Rehab 815 Replacement is anticipated 4th quarter of FY 21-22, City Hall Phase I Design and Security has security complete but work space evaluation delayed due to staff capacity, DPW design concepts are being finalized, Library Phase 1 Part 1 had no bids again on March 30