Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.

Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.

Sources and supporting records

3 official source references across 3 official documents.

May 8, 2019 · action datePage 20

Mason City Council

Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.

View official source ↗
May 8, 2019 · action datePage 8

Mason City Council

Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.

View official source ↗
May 8, 2019 · action datePage 35

Mason City Council

Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.