July 20, 2020 · official recordActor not established1 official source reference
Status: completed
City Manager role: reported update
Official record
Reported that for Center Street from Walnut Street to N. Bush Street, concrete work was completed, base course of asphalt was to be laid the week of July 20th, and wear course asphalt was to be completed by end of July.
Status: completed
City Manager role: reported update
1 official source reference across 1 official document.
Reported that for Center Street from Walnut Street to N. Bush Street, concrete work was completed, base course of asphalt was to be laid the week of July 20th, and wear course asphalt was to be completed by end of July.