Status: planned
City Manager role: reported update
Official record
Reported that Replace PLCs on 3 Wells and Well No. 6 Rebuild have anticipated start dates in Spring of 2021, that completion of the Gutters for Water Treatment Plant project is set for the week of April 5th, that South Water Tower Repair is preparing documents for bid advertising, that staff is drafting a Request for Proposal for the Wastewater Treatment Plant - Design
Status: planned
City Manager role: reported update
1 official source reference across 1 official document.
Reported that Replace PLCs on 3 Wells and Well No. 6 Rebuild have anticipated start dates in Spring of 2021, that completion of the Gutters for Water Treatment Plant project is set for the week of April 5th, that South Water Tower Repair is preparing documents for bid advertising, that staff is drafting a Request for Proposal for the Wastewater Treatment Plant - Design
View official source ↗