Reported that all underground work is completed, main line curb is done

Reported that all underground work is completed, main line curb is done, radii at Howell and Cedar will be completed within a week or so, and the next step will be base course of asphalt, then pathway work.

June 15, 2020 · official recordActor not established1 official source reference

Status: completed

City Manager role: reported update

Sources and supporting records

1 official source reference across 1 official document.

June 15, 2020 · official recordPage 87

Mason City Council

Reported that all underground work is completed, main line curb is done, radii at Howell and Cedar will be completed within a week or so, and the next step will be base course of asphalt, then pathway work.