Reported that the Turbine Aeration Blower at POTW is advertised for bid with a bid opening scheduled for November 6, that hydrants at Mason Plaza are being secured by easement, that Well No. 6 Rebuild and Gutters for Water Treatment Plant have not started, that sewer flow data collection on Mason St. is underway with Wolverine Engineering & Surveyors
Status: started
City Manager role: reported update
1 official source reference across 1 official document.
Reported that the Turbine Aeration Blower at POTW is advertised for bid with a bid opening scheduled for November 6, that hydrants at Mason Plaza are being secured by easement, that Well No. 6 Rebuild and Gutters for Water Treatment Plant have not started, that sewer flow data collection on Mason St. is underway with Wolverine Engineering & Surveyors