April 21, 2025 · official recordActor not established1 official source reference
Status: in progress
City Manager role: reported update
Official record
Reported that 2019-U3b WWTP Plant Construction was in progress with regular check-ins, 2023-U10 Water Service Line Replacement was in progress with 29 of 30 complete, and 2023-U13 Plant Valves and Baffle Wall Repair was in progress with valves complete.
Status: in progress
City Manager role: reported update
1 official source reference across 1 official document.
Reported that 2019-U3b WWTP Plant Construction was in progress with regular check-ins, 2023-U10 Water Service Line Replacement was in progress with 29 of 30 complete, and 2023-U13 Plant Valves and Baffle Wall Repair was in progress with valves complete.