2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

Sources and supporting records

12 official source references across 12 official documents.

May 1, 2023 · official recordPage 69

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
April 17, 2023 · official recordPage 105

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
March 20, 2023 · official recordPage 217

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
January 16, 2023 · official recordPage 52

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
December 19, 2022 · official recordPage 66

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
November 21, 2022 · official recordPage 120

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
November 9, 2022 · official recordPage 47

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
August 15, 2022 · official recordPage 54

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
August 3, 2022 · official recordPage 13

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
July 5, 2022 · official recordPage 29

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
June 20, 2022 · official recordPage 85

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗
October 18, 2021 · official recordPage 44

Mason City Council

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

View official source ↗