Reported that interior renovation work related to Phase II is anticipated to be completed by the end of March

Reported that interior renovation work related to Phase II is anticipated to be completed by the end of March, that CADL anticipates re-opening after furniture is installed, and that CADL/City are continuing to apply for a grant while CADL launches a fundraising campaign.

April 1, 2024 · official recordActor not established1 official source reference

Status: planned

City Manager role: reported update

Sources and supporting records

1 official source reference across 1 official document.

April 1, 2024 · official recordPage 49

Mason City Council

Reported that interior renovation work related to Phase II is anticipated to be completed by the end of March, that CADL anticipates re-opening after furniture is installed, and that CADL/City are continuing to apply for a grant while CADL launches a fundraising campaign.

View official source ↗