Status: completed
City Manager role: reported update
Official record
The report listed completed street projects including Center Street-Walnut St to N. Bush St, Brookdale St.-W. South St to Willow St, Cherry-McRoberts St to Henderson St, Eaton Drive, W. Elm St.-McRoberts St to Lansing St, E. Maple-S. Jefferson to S. Barnes, Henderson Street, and the alley W. Columbia to W. Sycamore, while Temple Street Pedestrian Crossing is in progress.
Status: completed
City Manager role: reported update
1 official source reference across 1 official document.
The report listed completed street projects including Center Street-Walnut St to N. Bush St, Brookdale St.-W. South St to Willow St, Cherry-McRoberts St to Henderson St, Eaton Drive, W. Elm St.-McRoberts St to Lansing St, E. Maple-S. Jefferson to S. Barnes, Henderson Street, and the alley W. Columbia to W. Sycamore, while Temple Street Pedestrian Crossing is in progress.