Status: in progress
City Manager role: reported update
Official record
Reported that 2017-P8 Laylin Park Improvements were preparing estimates for final work, 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) and 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension were in progress, 2018-P3 Planning: 5 yr Parks/Recreation Plan was not started, and 2018-P5 City Tree Evaluation was preparing bids.
Status: in progress
City Manager role: reported update
1 official source reference across 1 official document.
Reported that 2017-P8 Laylin Park Improvements were preparing estimates for final work, 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) and 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension were in progress, 2018-P3 Planning: 5 yr Parks/Recreation Plan was not started, and 2018-P5 City Tree Evaluation was preparing bids.
View official source ↗