Official minutes · September 21, 2026Deborah S. Stuart1 official source reference
Status: official minutes confirmed
City Manager role: authorized to act
Official record
Authorized the City Manager to execute change orders to the contract for construction of the proposed wastewater system improvements project with Christman Constructors, Inc., in an amount not to exceed a total of $1,500,000 of the designated contingency.
Status: official minutes confirmed
City Manager role: authorized to act
1 official source reference across 1 official document.
Authorized the City Manager to execute change orders to the contract for construction of the proposed wastewater system improvements project with Christman Constructors, Inc., in an amount not to exceed a total of $1,500,000 of the designated contingency.
View official source ↗