Project 2021 U1

A source-backed timeline of City of Mason records explicitly connected to Project 2021 U1 in Civic Core.

6 official records0 primary6 supportingOctober 18, 2021 – March 20, 2023

How this dossier is built

Deb Tracker groups records here only when the audited record explicitly matches this named subject. The underlying civic events remain separate, and every timeline entry links back to its source-backed record page.

TimelineChronological source-backed history · oldest to newest
July 5, 2022 · documented dateSupporting contextActor not establisheddelayed

2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.

Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.