Status: delayed
City Manager role: reported update
Official record
Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.
Status: delayed
City Manager role: reported update
1 official source reference across 1 official document.
Reported that 2017-U15 Replace Hydrants and Mason Plaza and 2017-U34 Well No. 5 Rebuild were completed, 2019-U3a Wastewater Treatment Plant – Design was in process with anticipated completion 2023, 2021-U1 WTP- High-Pressure Pump VFD had anticipated completion in December 2023, and 2021-U2 WTP- Replacement of Valves was placed on hold to do another CIP project that has recently become a priority.
View official source ↗