Shared Deb Tracker result
Can you tell me about the roads?
Created August 20, 202616 retrieved public records10 cited in the answer
Records preserved with this result
These are the public records that were retrieved for the question when this result was created.
Official recordNovember 26, 2018Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported status updates for South St to Northbrook to City Limits, Avon Street, Northbrook to Carom Circle, S. Jefferson to Oak Street to Kipp Road, and Sidewalk Program - Summerwood.
infrastructure
Official recordJuly 15, 2019Cited in answer1 source-backed factcontractorCity Manager role: outside information relayed
Reported that Summerwood and Downtown are completed, while restoration and pavement patching in Summerwood remains and the contractor is transitioning into Laylin Park in upcoming weeks.
infrastructure
Official recordMay 16, 2022Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
The notice explains that work will include street reconstruction, concrete work, sidewalk replacement as needed, ADA-compliant sidewalk ramps, phases beginning mid-May and late summer, and a warning that dates are estimates and weather dependent.
infrastructure
Official recordSeptember 20, 2021Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported status and completion timing for several FY 2021-2022 streets/sidewalks/signals projects, including a planned pulverizing schedule and final asphalt work timing.
infrastructure
Official recordMay 8, 2019Cited in answer3 source-backed factsUnderlying actor not establishedCity Manager role: reported update
Reported that the 2017-S9 S. Jefferson - Oak Street to Kipp Road project cannot begin construction before June 9 per contract and that a pre-construction meeting is scheduled for May 8.
infrastructure
Official recordJuly 20, 2020Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported that Kerns Road was graded and base course for the road was to be put down the week of July 13 for the Kerns Road- Cedar Street to Howell Rd./ Hayhoe Riverwalk Trail Extension project.
infrastructure
Official recordApril 20, 2020Cited in answer1 source-backed factcontractorCity Manager role: outside information relayed
For Kerns Road to Howell Rd. and the Hayhoe Riverwalk Trail Extension, the contractor is in place, permits are renewed, the schedule has been received and distributed, a preconstruction meeting was held April 14, 2020, and construction at Howell Road is scheduled to begin on April 20, 2020.
infrastructure
Official recordApril 17, 2017Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: unclear
The resolution states that the City Administrator recommends waiving the Columbia Street special assessment for new sidewalk placement to keep the street program on schedule.
infrastructure
Official recordJuly 20, 2020Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported that for W. Elm Street from McRoberts Street to Lansing Street, the road has been marked and pulverizing was to start the week of July 20th.
infrastructure
Official recordJuly 20, 2020Cited in answer1 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported that for Center Street from Walnut Street to N. Bush Street, concrete work was completed, base course of asphalt was to be laid the week of July 20th, and wear course asphalt was to be completed by end of July.
infrastructure
Official recordMarch 6, 20171 source-backed factDeborah StuartCity Manager role: recommendation
Stuart informed Council regarding the proposed Traffic Control Order to designate Steele Street between Oak and Elm streets as a school loading zone.
infrastructure
Official recordNovember 6, 20241 source-backed factMason City CouncilCity Manager role: no substantive role
the American Legion Post 148 said this year's parade will not occur and the council-approved road closures are no longer necessary.
infrastructure
Official recordFebruary 15, 20211 source-backed factUnderlying actor not establishedCity Manager role: reported update
Stuart reported that meetings must continue to be virtual at least until February 21, 2021 per the current orders, that masks are still required to be worn in City Hall even if you have received a vaccine, that the City was still looking into the Jail Complex project and whether a third party or the State Permitting will need to take this project on, and that the City was unable to purchase the property on N. Mason Street.
infrastructure
Official recordJanuary 18, 20211 source-backed factUnderlying actor not establishedCity Manager role: reported update
Reported that the public comment received from Ms. Fouche on January 18, 2021 was evaluated, that the property and street meet legal requirements, and that the City cannot require MDOT or the property owner to make changes.
infrastructure
Official recordApril 6, 20201 source-backed factUnderlying actor not establishedCity Manager role: unclear
Payments can be made by mail, online, by phone (833.699.7827), or can be dropped off in the drop box located outside of City Hall, 201 West Ash Street, Mason, MI 48854.
infrastructure
Official recordOctober 21, 20191 source-backed factUnderlying actor not establishedCity Manager role: reported update
Stuart reported that the MDOT Bids for the pedestrian crossings on Temple Street came back significantly higher than anticipated and that staff will need to regroup and evaluate the scope of the project to determine what next steps should be taken.
infrastructure
Want the latest answer?This page is a snapshot. Deb Tracker may contain newer records after this result was created.
Ask with latest records →