Search the retained City Manager and City Administrator reports extracted from Mason City Council packets. These are source documents, not standalone claims or curated timeline events. Deb Tracker keeps the original packet link and report-page range attached so the public record can be checked against its source.

226 retained reportsShowing 191–200 · Page 20 of 23
City Manager ReportMarch 18, 2019City ManagerPacket pages 112–114

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: March 15, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Grant Agreement has been signed. Public Project Ground Breaking is scheduled for March 22nd at 11 am. Council is encouraged to attend. 201 W. Ash Cit

Read extracted report text

City Manager’s Report: March 15, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Grant Agreement has been signed. Public Project Ground Breaking is scheduled for March 22nd at 11 am. Council is encouraged to attend. 201 W. Ash City Hall Anticipate installation of equipment to begin this spring 154 W. Maple (former shoe store) Building permit has been issued. A Right of Way Permit is expected to be submitted next which will include a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 652 Hull Rd New Goodwill Staff anticipates a building permit application once supplemental permits from the State and County have been obtained. 400 S. Cedar St Harvey Education Center / Mason Public Schools State building permit active for construction of new addition as part of the Phase 1 Bond Project. More information available at: http://bondprojects.masonk12.net/. MDOT – Ash/Cedar (M-36) MDOT has started the signal upgrade project at the intersection of Ash and Cedar (M-36) next week. The Contractor completed installation of the signal foundations. The signals themselves and the sidewalk work will take place at a later time TBD. This 2nd phase of work will take approximately 1-2 weeks and will have the following traffic impacts: Periodic daily lane closures on M-36 for the Contractor to perform the work. The intersection will not be closed at any time and traffic will be maintained through the intersection. 801 N. Cedar St. (City Limits) City Limits, has requested final site plan approval to construct a 4,828 square foot addition along with additional parking. The project is currently on hold as staff is waiting for additional information from the applicant. 118 W. Oak St. (Old MPS Admin. Bldg.) The Planning Commission held a public hearing on March 12, 2019 to consider a request from applicant, David Meredith, WCH, LLC, to rezone the property from an O-1: General office district to a C-1: Central business district. They recommend that City Council approve Ordinance 226 which provides for the re-zoning of the property. City Council will hold a 2nd reading of Ordinance 226 on Monday, March 18. SUBDIVISIONS Subdivisions require three stages of approval before site plan approval and building permits can be issued: (1) Tentative Preliminary Plat, (2) Final Preliminary Plat, (3) Final Plat. Enclave at Rayner Ponds Subdivision (19 lots, 1 park) The City has approved a Tentative Preliminary Plat (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Rayner Ponds – Phase 4 Subdivision (16 lots) The City approved a Tentative Preliminary Plat in January of 2018 (Stage 1). Staff received an application for Final Preliminary Plat (Stage 2) in December of 2018. A public hearing was held by the Planning Commission on January 15 resulting in a recommendation for approval to City Council. City Council approved the Final Preliminary Plat on January 21, 2019. The applicant will submit a Final Plat for approval (Stage 3) next. 116 OPERATIONS AND COMMUNITY RELATIONS • The MML- 2019 Capital Conference in Lansing will be March 19 and 20, 2019. The representatives from Mason will be City Manager Stuart, Mayor Whipple, and Councilmembers Brown, Ferris, and Schaffer. • April 13, 2019 (Saturday) is tentatively planned for the 2019 Budget meeting; please hold the date. Staffing Updates: • Open Positions: Police Officer position has been offered and accepted, background check is in process; Project Specialist applications are under review and interviews will be set-up soon; Part-Time Code Enforcement/Community Resource Officer interviews have taken place. LARGE CITY PROJECTS FY 2018-2019 Project Project Name/Description Status Completed STREETS, SIDEWALKS, BRIDGES (S) 2017-S6 South St - Northbrook to City Limits Complete Sep 2017-S7 Avon Street - All Complete Sep 2017-S8 Northbrook - South to Carom Circle Complete Sep 2017-S9 S. Jefferson - Oak Street to Kipp Road Cannot begin construction before June 9 per contract. Pre-Con meeting will be held in May. 2017-S10 Sidewalk Program - Summerwood Notice of Award sent to Contractor – Awaiting return of bonds and insurances 2018-S1 MDOT- Temple Street Safety Grant MDOT Grade Inspection has been completed 2018-S32 Columbia - Cedar to US 127 Complete Sep UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) 2018-U1 Utilities for Properties on Kipp Road Complete Sep 2017-U3.2 Waste Water Treatment Plant Upgrades Complete Oct 2017-U3.3 Design of the New DPW Facility Delayed until future FY N/A 2017-U6 Abandon Wells by Airport Delayed until future FY N/A 2017-U9 Northbrook - South to Carom Circle Complete Sep 2017-U10 S. Jefferson - Oak St to Kipp Road See 2017-S9 2017-U12 300,000 G Storage Tank Top Sealing Delayed until future FY N/A 2017-U13 Well No. 7 Rebuild Well work is complete. The motor is on order. 2017-U15 Replace Two Fire Hydrants Behind Mason Plaza Delayed until future FY N/A 2017-U16 Cathodic Protection for Ground Storage Tank Planning stage 2017-U17 High Service Pump No. 1 Rebuild In progress 2017-U18 Replace Chlorine Analyzer Complete Aug 2018-U35 BS&A Work Order Application Award of project anticipated in May 2018-U36 Sewer Push Camera Replacement Complete Nov 2018-U37 Log Jam Removal Sycamore Creek Complete Nov PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) 2017-P8 Laylin Park Improvements Staff is evaluating final work priorities for the spring. 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) Complete Nov 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension Complete Nov 2018-P3 Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements In progress 2018-P5 City Tree Evaluation Notice of Award Sent to Contractor – Awaiting return of Insurances MOTOR VEHICLE POOL (MVP) 2017-MVP6 1/2 Ton 2x4 Pickup Truck Complete Sep 117 2017-MVP7 Mower Complete Jul 2017-MVP8 Police Cars Complete Jan 2017-MVP9 Large Items (Leaf Vacuum) Complete Nov 2017-MVP10 5-yard Dump/Plow Truck Cab/Chassis Ordered 2017-MVP18 Command Vehicle Complete Oct 2017-MVP30 Front End Material Loader Complete Nov BUILDING, PROPERTY, EQUIPMENT (B) 2017-B1 Library- Facility Evaluation A public open house will be held on Tuesday, March 12, 2019 to gain feedback on the results of the library feasibility study 2017-B3.1 Police: Portable Radios Complete Oct 2017-B4 City Hall Landscaping and Lighting Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. 2017-B6 Fire: Fire Engine 809/Tower 808 City Council Approved Change Order, Feb 18 2018-B4 IT: BS&A Timesheet Program Not started, connection issues with offsite facilities 2018-B4 IT: BS&A Cemetery and HR Upgrade Complete Nov 2018-B6 IT: AV Room Technology Patch Evaluation is complete; staff are reviewing 2018-B7 Planning: Cedar/127 Corridor (Transportation and Land Use) Moved to 2019-2021 – integrate with master plan N/A 2018-B24 City Hall Rental Space Furniture Replacement Old rectangle tables have been replaced with plastic ones. New chairs are currently being evaluated. FY 2019-2020 Project Project Name/Description Status Completed 2019 Local Streets Seeking City Council Approval of Award, Mar 4, 2019 118

City Manager ReportMarch 4, 2019City ManagerPacket pages 36–37

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: March 1, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require thre

Read extracted report text

City Manager’s Report: March 1, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require three stages of approval before site plan approval and building permits can be issued: (1) Tentative Preliminary Plat, (2) Final Preliminary Plat, (3) Final Plat. Enclave at Rayner Ponds Subdivision (19 lots, 1 park) The City has approved a Tentative Preliminary Plat (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Rayner Ponds – Phase 4 Subdivision (16 lots) The City approved a Tentative Preliminary Plat in January of 2018 (Stage 1). Staff received an application for Final Preliminary Plat (Stage 2) in December of 2018. A public hearing was held by the Planning Commission on January 15 resulting in a recommendation for approval to City Council. City Council approved the Final Preliminary Plat on January 21, 2019. The applicant will submit a Final Plat for approval (Stage 3) next. 154 W. Maple (former shoe store) Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 652 Hull Rd New Goodwill The City of Mason and Vevay Township Joint Planning Commission met on 2/12/2019 and approved Resolution 2019-01, approving a preliminary site plan, final site plan, and special use permit for Goodwill Industries of Central Michigan’s Heartland, Inc. to construct a new 15,772 square foot commercial building located at 652 Hull Road. 400 S. Cedar St Harvey Education Center / Mason Public Schools State building permit active for construction of new addition as part of the Phase 1 Bond Project. More information available at: http://bondprojects.masonk12.net/. MDOT – Ash/Cedar (M-36) MDOT has started the signal upgrade project at the intersection of Ash and Cedar (M-36) next week. The Contractor completed installation of the signal foundations. The signals themselves and the sidewalk work will take place at a later time TBD. This 2nd phase of work will take approximately 1-2 weeks and will have the following traffic impacts: Periodic daily lane closures on M-36 for the Contractor to perform the work. The intersection will not be closed at any time and traffic will be maintained through the intersection. 801 N. Cedar St. (City Limits) City Limits, has requested a preliminary/final site plan approval to construct a 4,828 square foot addition along with additional parking. The project will be reviewed at the March 12, 2019 Planning Commission meeting. 118 W. Oak St. (Old MPS Admin. Bldg.) The Planning Commission will hold a public hearing on March 12, 2019 to consider a request from applicant, David Meredith, WCH, LLC, to rezone the property from an O-1: General office district to a C-1: Central business district. 37 OPERATIONS AND COMMUNITY RELATIONS • March 9, 2019 at 8:30 am (Saturday) Planning Commission and Councilmember Tour of Large Capital Projects proposed in CIP. If you would like to attend, you must contact Dana Martin by Wednesday, March 6th so we can coordinate the

City Manager ReportFebruary 18, 2019City ManagerPacket pages 39–41

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: February 15, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require

Read extracted report text

City Manager’s Report: February 15, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require three stages of approval before site plan approval and building permits can be issued: (1) Tentative Preliminary Plat, (2) Final Preliminary Plat, (3) Final Plat. Enclave at Rayner Ponds Subdivision (19 lots, 1 park) The City has approved a Tentative Preliminary Plat (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Rayner Ponds – Phase 4 Subdivision (16 lots) The City approved a Tentative Preliminary Plat in January of 2018 (Stage 1). Staff received an application for Final Preliminary Plat (Stage 2) in December of 2018. A public hearing was held by the Planning Commission on January 15 resulting in a recommendation for approval to City Council. City Council approved the Final Preliminary Plat on January 21, 2019. The applicant will submit a Final Plat for approval (Stage 3) next. 154 W. Maple (former shoe store) Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 652 Hull Rd New Goodwill The City of Mason and Vevay Township Joint Planning Commission met on 2/12/2019 and approved Resolution 2019-01, approving a preliminary site plan, final site plan, and special use permit for Goodwill Industries of Central Michigan’s Heartland, Inc. to construct a new 15,772 square foot commercial building located at 652 Hull Road. 400 S. Cedar St Harvey Education Center / Mason Public Schools State building permit active for construction of new addition as part of the Phase 1 Bond Project. More information available at: http://bondprojects.masonk12.net/. MDOT – Ash/Cedar (M-36) MDOT has started the signal upgrade project at the intersection of Ash and Cedar (M-36) next week. The Contractor completed installation of the signal foundations. The signals themselves and the sidewalk work will take place at a later time TBD. This 2nd phase of work will take approximately 1-2 weeks and will have the following traffic impacts: Periodic daily lane closures on M-36 for the Contractor to perform the work. The intersection will not be closed at any time and traffic will be maintained through the intersection. OPERATIONS AND COMMUNITY RELATIONS • March 19-20, 2019 will be the MML- 2019 Capital Conference. Councilmembers, please let Dana Martin know if you wish to attend by February 22nd. • April 13, 2019 (Saturday) is tentatively planned for the 2019 Budget meeting; please hold the date. • Councilmember Tours: As we prepare for the budget, it can be helpful to get a tour of our facilities. If you would like the City Manager Stuart to provide that tour, please contact Dana Martin to coordinate a time that works for the group. • There will be a May 7, 2019 Special Election for the Mason Public School Operating Millage Proposal - This proposal will allow the school district to continue to levy the statutory rate of not to exceed 18 mills on all property, except principal residence and other property exempted by lawn, required for the school district to receive its full revenue per pupil 39 foundation allowance and restores millage lost as a result of the reduction required by the Michigan Constitution of 1963. Staffing Updates: • New Hires/ Promotions/ Retirements: None • Open Positions: DPW Laborer Position has been offered and accepted – going through background checks and pre- employment physical/drug testing, Project Specialist position closed internally and applicants are being reviewed, Part- Time Code Enforcement/Community Resource Officer position was posted with posting closing February 27. LARGE CITY PROJECTS FY 2018-2019 Project Project Name/Description Status Completed STREETS, SIDEWALKS, BRIDGES (S) 2017-S6 South St - Northbrook to City Limits Complete Sep 2017-S7 Avon Street - All Complete Sep 2017-S8 Northbrook - South to Carom Circle Complete Sep 2017-S9 S. Jefferson - Oak Street to Kipp Road Cannot begin construction before June 9 per contract. Pre-Con meeting will be held in May. 2017-S10 Sidewalk Program - Summerwood Seeking City Council Approval of Award, Feb 4, 2019 2018-S1 MDOT- Temple Street Safety Grant Project is funded for FY19 (Oct. 1- Sept. 30). Working on revisions for MDOT submittal. 2018-S32 Columbia - Cedar to US 127 Complete Sep UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) 2018-U1 Utilities for Properties on Kipp Road Complete Sep 2017-U3.2 Waste Water Treatment Plant Upgrades Complete Oct 2017-U3.3 Design of the New DPW Facility Delayed until next FY N/A 2017-U6 Abandon Wells by Airport Delayed until next FY N/A 2017-U9 Northbrook - South to Carom Circle Complete Sep 2017-U10 S. Jefferson - Oak St to Kipp Road See 2017-S9 2017-U12 300,000 G Storage Tank Top Sealing Delayed until next FY N/A 2017-U13 Well No. 7 Rebuild Well work is complete. The motor is on order. 2017-U15 Replace Two Fire Hydrants Behind Mason Plaza Delayed until next FY N/A 2017-U16 Cathodic Protection for Ground Storage Tank Planning stage 2017-U17 High Service Pump No. 1 Rebuild In progress 2017-U18 Replace Chlorine Analyzer Complete Aug 2018-U35 BS&A Work Order Application Award of project anticipated in March/April 2018-U36 Sewer Push Camera Replacement Complete Nov 2018-U37 Log Jam Removal Sycamore Creek Complete Nov PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) 2017-P8 Laylin Park Improvements Staff is evaluating final work priorities for the spring. 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) Complete Nov 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension Complete Nov 2018-P3 Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements In progress 2018-P5 City Tree Evaluation In Process of Awarding Bid MOTOR VEHICLE POOL (MVP) 2017-MVP6 1/2 Ton 2x4 Pickup Truck Complete Sep 2017-MVP7 Mower Complete Jul 40 2017-MVP8 Police Cars Complete Jan 2017-MVP9 Large Items (Leaf Vacuum) Complete Nov 2017-MVP10 5-yard Dump/Plow Truck Cab/Chassis Ordered 2017-MVP18 Command Vehicle Complete Oct 2017-MVP30 Front End Material Loader Complete Nov BUILDING, PROPERTY, EQUIPMENT (B) 2017-B1 Library- Facility Evaluation In progress 2017-B3.1 Police: Portable Radios Complete Oct 2017-B4 City Hall Landscaping and Lighting Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. 2017-B6 Fire: Fire Engine 809/Tower 808 Seeking City Council Approval of Change Order, Feb 18 2018-B4 IT: BS&A Timesheet Program Not started, connection issues with offsite facilities 2018-B4 IT: BS&A Cemetery and HR Upgrade Complete Nov 2018-B6 IT: AV Room Technology Patch Evaluation is complete; staff are reviewing 2018-B7 Planning: Cedar/127 Corridor (Transportation and Land Use) Moved to 2019-2021 – integrate with master plan 2018-B24 City Hall Rental Space Furniture Replacement Old rectangle tables have been replaced with plastic ones. New chairs are currently being evaluated. FY 2019-2020 Project Project Name/Description Status Completed 2019 Local Streets In bidding process 41

City Manager ReportFebruary 4, 2019City ManagerPacket page 64

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: February 1, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require t

Read extracted report text

City Manager’s Report: February 1, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Two building permits are active for interior and exterior renovations to restore two entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. 402 S. Jefferson (former Baja Grill) Project is on track for grant authorization. 201 W. Ash City Hall Anticipate installation of equipment to begin this winter. Subdivisions require three stages of approval before site plan approval and building permits can be issued: (1) Tentative Preliminary Plat, (2) Final Preliminary Plat, (3) Final Plat. Enclave at Rayner Ponds Subdivision (19 lots, 1 park) The City has approved a Tentative Preliminary Plat (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Rayner Ponds – Phase 4 Subdivision (16 lots) The City approved a Tentative Preliminary Plat in January of 2018 (Stage 1). Staff received an application for Final Preliminary Plat (Stage 2) in December of 2018. A public hearing was held by the Planning Commission on January 15 resulting in a recommendation for approval to City Council. City Council approved the Final Preliminary Plat on January 21, 2019. The applicant will submit a Final Plat for approval (Stage 3) next. 154 W. Maple (former shoe store) Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 652 Hull Rd New Goodwill The City of Mason and Vevay Township Joint Planning Commission will conduct a public hearing on Tues, Feb 12, at 6:30 p.m., at City Hall. The purpose of the hearing is to receive

City Manager ReportJanuary 21, 2019City ManagerPacket page 3

MANAGER’S REPORT

Source attribution: City Manager Report during Deborah S. Stuart's tenure

MANAGER’S REPORT: 1/04/2019 Stuart reported that Chief Kerry Minshall has been selected as the Mason Chamber of Commerce’s Citizen of the Year and would encourage council members to attended the MACC Banquet on February 7, 2019. Stuart reported that the joint CIP meeting between the City Council and the Planning Commission will take place on Monday, February 11, 2019 at 6:30 p.m. Stuart also announced that the MML Capital Conference will be March 19-20, 2019 and anyone who wishes to attend should notify her as soon as possible.

Read extracted report text

MANAGER’S REPORT: 1/04/2019 Stuart reported that Chief Kerry Minshall has been selected as the Mason Chamber of Commerce’s Citizen of the Year and would encourage council members to attended the MACC Banquet on February 7, 2019. Stuart reported that the joint CIP meeting between the City Council and the Planning Commission will take place on Monday, February 11, 2019 at 6:30 p.m. Stuart also announced that the MML Capital Conference will be March 19-20, 2019 and anyone who wishes to attend should notify her as soon as possible.

City Manager ReportJanuary 21, 2019City ManagerPacket page 63

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: January 21, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. A second building permit will be issued to restore a doorway on the north end of the façade. The Historic District Commission will review the façade change at their next meeting on January 21. 402 S. Jeffe

Read extracted report text

City Manager’s Report: January 21, 2019 ACTIVE PROJECTS STATUS UPDATES (PROJECTS NOT COORDINATED BY THE CITY) Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. A second building permit will be issued to restore a doorway on the north end of the façade. The Historic District Commission will review the façade change at their next meeting on January 21. 402 S. Jefferson (former Baja Grill) Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to co-locate on the radio tower has been signed and a building permit has been issued. Anticipate installation of equipment to begin this winter. Pending Subdivisions: Enclave at Rayner Ponds (19 lots, 1 park) and Rayner Ponds – Phase 4 (16 lots) Subdivisions require three stages of approval before site plan approval and building permits can be issued – Tentative Preliminary Plat/Final Preliminary Plat/Final Plat. Current stage for both: The City has approved a Tentative Preliminary Plat for both projects (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Staff has received an applicant for a Final Preliminary Plat for Rayner Ponds – Phase 4 and held a public hearing on January 15. 154 W. Maple (former shoe store) The Planning Commission approved the Final Site Plan on December 11 meeting. Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 118 W Oak Former school administration building Two applications received - one to re-zone the property to C1 Central Business District, the second for Final Site Plan approval for the use of the property as an entertainment venue with an escape room on the 2nd floor and arcade on the first floor. The application has been returned due to lack of information. Staff will continue to work with the property owner. A new application may be submitted in the future. Project will be removed in next report. 652 Hull Rd New Goodwill The City of Mason and Vevay Township Joint Planning Commission will conduct a public hearing on Tues, Feb 12, at 6:30 p.m., at City Hall. The purpose of the hearing is to receive

City Manager ReportJanuary 7, 2019City ManagerPacket pages 8–18

City Manager’s Report

Source attribution: City Manager Report during Deborah S. Stuart's tenure

City Manager’s Report: January 4, 2019 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to co-

Read extracted report text

City Manager’s Report: January 4, 2019 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to co-locate on the radio tower has been signed and a building permit has been issued. Anticipate installation of equipment to begin this winter. Pending Subdivisions: Enclave at Rayner Ponds (19 lots, 1 park) and Rayner Ponds – Phase 4 (16 lots) Subdivisions require three stages of approval before site plan approval and building permits can be issued – Tentative Preliminary Plat/Final Preliminary Plat/Final Plat. Current stage for both: The City has approved a Tentative Preliminary Plat for both projects (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Staff anticipates the applicant will submit a Final Preliminary Plat for Rayner Ponds – Phase 4 in December. 154 W. Maple (former shoe store) The Planning Commission approved the Final Site Plan on December 11 meeting. Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 118 W Oak Former school administration building Two applications received - one to re-zone the property to C1 Central Business District, the second for Final Site Plan approval for the use of the property as an entertainment venue with an escape room on the 2 nd floor and arcade on the first floor. Staff is working with applicant to obtain complete information necessary for evaluating the proposal. OPERATIONS AND COMMUNITY RELATIONS • A Public Hearing will be held on Tuesday, January 15, 2019 regarding a preliminary plat for future development as part of Phase 4 of the existing Rayner Ponds Estates development (notice attached). • February 7, 2019 will be the MACC 2019 Awards Dinner (notice attached). Among other Awards and Recognitions, Fire Chief, Kerry Minshall, will be awarded The Citizen of the Year Award. Councilmembers, please let Dana Martin know if you wish to attend by January 17th . • February 11, 2019 is tentatively planned for the joint City Council and Planning Commission meeting for the Continuous Improvement Plan (CIP) review; please hold the date. • March 19-20, 2019 will be the MML- 2019 Capital Conference. Councilmembers, please let Dana Martin know if you wish to attend by February 22nd . • Summary from MML of legislation that was passed in the last few months is attached for your reference. Staffing Updates: • New Hires/Promotions: Jeff Rewerts was promoted to Utility Foreman- POTW effective January 6, 2019. • Open Positions: Police Officer position has been posted, applications due by January 11, 2019. DPW Laborer position has been posted, applications due by January 4, 2019. LARGE PUBLIC PROJECTS FY 2018-2019 Project Project Name/Description Status Completed STREETS, SIDEWALKS, BRIDGES (S) 2017-S6 South St - Northbrook to City Limits Complete Sep 2017-S7 Avon Street - All Complete Sep 2017-S8 Northbrook - South to Carom Circle Complete Sep 2017-S9 S. Jefferson - Oak Street to Kipp Road Project has been let through the MDOT system. Rieth Riley is low bidder. 2017-S10 Sidewalk Program - Summerwood Documents prepared for a Jan advertisement and spring construction. 2018-S1 MDOT- Temple Street Safety Grant Project is funded for FY19 (Oct. 1- Sept. 30). Package to be submitted to MDOT. 2018-S32 Columbia - Cedar to US 127 Complete Sep MDOT – South Street Bridge Repair Complete Nov MDOT – Cedar/Ash intersection MDOT does not have a start date yet. MDOT – Steele Street signaled pedestrian crossing Complete Aug UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) 2018-U1 Utilities for Properties on Kipp Road Complete Sep 2017-U3.2 Waste Water Treatment Plant Upgrades Complete Oct 2017-U3.3 Design of the New DPW Facility After 2017-U3 2017-U6 Abandon Wells by Airport Project on hold; filed FAA permit to do work – up to 45-day response period. 2017-U9 Northbrook - South to Carom Circle Complete Sep 2017-U10 S. Jefferson - Oak St to Kipp Road See 2017-S9 2017-U12 300,000 G Storage Tank Top Sealing Delayed until next FY N/A 2017-U13 Well No. 7 Rebuild Well work is complete. The motor is on order. 2017-U15 Replace Two Fire Hydrants Behind Mason Plaza Work scheduled for spring construction 2017-U16 Cathodic Protection for Ground Storage Tank Planning stage. 2017-U17 High Service Pump No. 1 Rebuild In progress 2017-U18 Replace Chlorine Analyzer Complete Aug 2018-U35 BS&A Work Order Application Award of project anticipated in December to coordinate with other projects involving BS&A software. 2018-U36 Sewer Push Camera Replacement Complete Nov 2018-U37 Log Jam Removal Sycamore Creek Complete Nov PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) 2017-P8 Laylin Park Improvements Staff is evaluating final work priorities for the spring. 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) Complete Nov 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension Complete Nov 2018-P3 Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements In progress 2018-P5 City Tree Evaluation Bid packets announcement will go out December 16 Bid opening January 4 2019. MOTOR VEHICLE POOL (MVP) 2017-MVP6 1/2 Ton 2x4 Pickup Truck Complete Sep 2017-MVP7 Mower Complete Jul 2017-MVP8 Police Cars On order 2017-MVP9 Large Items (Leaf Vacuum) Complete Nov 2017-MVP10 5-yard Dump/Plow Trucks Cab/Chassis (City Council consideration 12.14.18) 2017-MVP18 Command Vehicle Complete Oct 2017-MVP30 Front End Material Loader Complete Nov BUILDING, PROPERTY, EQUIPMENT (B) 2017-B1 Library- Facility Evaluation In progress 2017-B3.1 Police: Portable Radios Complete Oct 2017-B4 City Hall Landscaping and Lighting Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. 2017-B6 Fire: Fire Engine 809/Tower 808 Recommendation to City Council 2018-B4 IT: BS&A Timesheet Program Not started, connection issues with offsite facilities 2018-B4 IT: BS&A Cemetery and HR Upgrade Complete Nov 2018-B6 IT: AV Room Technology Patch Evaluation is complete; staff are reviewing 2018-B7 Planning: Cedar/127 Corridor (Transportation and Land Use) Drafting scope/RFP 2018-B24 City Hall Rental Space Furniture Replacement Not started, evaluation planned during winter CITY OF MASON NOTICE OF PUBLIC HEARING The Mason Planning Commission will hold a public hearing on Tuesday, January 15, 2019, at 6:30 p.m. or as soon thereafter as possible in the City Hall Council Chambers, 201 W. Ash Street, Mason, Michigan, to receive public comment on a preliminary plat creating 20 residential lots, one common area, and one remaining parcel for future development as part of Phase 4 of the existing Rayner Ponds Estates development to be located on the following described property in the City of Mason: N 120 RDS OF S/E 1/4 OF SEC 4 EXC PLATS OF RAYNER PONDS ESTATES NO 2 RAYNER PONDS ESTATES NO 3 & RAYNER PONDS SANCTUARY. ALSO EXC BEG AT PT ON NS 1/4 LN NOD28'58"E 660.13 FT FROM S 1/4 COR OF SEC 4 - N0D28'58"E 1982.19 FT TO CEN OF SEC - S89D23'32"E ALNG EW 1/4 LN 730.04 FT - S0D36'28"W 50.22 FT - S60DW 70 FT - S13D53'08"W 415.29 FT - S30DE 70 FT - S32D22'45"W 227.48 FT - S15DE 15.23 FT - SW'LY 116.82 FT ALNG 292.5 FT RAD CURVE TO LEFT, CHD BRG S63D33'30"W 116.05 FT - S52D07'01"W 29.51 FT - SE'LY 165.22 FT ALNG 508 FT RAD CURVE TO RT, CHD BRG S 34D12'51"E 164.5 FT - S65D06'13"W 201 FT - S12D16'47"E 134.11 FT - S12D57'13"W 134.11 FT - S35D00'45"W 100.73 FT - S45D32'42"E 135 FT - S44D27'18"W 66 FT - S45D32'42"E 66 FT - S44D27'18"W 99.46 FT - S0D29'W 328.36 FT - N89D14'20"W 251.5 FT TO POB. FUTURE PHASES, RAYNER POND SANCTUARY, SEC 4, T2NR1W CITY OF MASON SPLIT ON 08/26/2002 FROM 33-19-10-04-426-001; FOR 2003 TIN: 33-19-10-04-426-002 Oral or written comments will be accepted at the Public Hearing. Written comments will also be received at the Community Development Department in person, by mail, or may be placed in the drop box located near the front doors of City Hall. The application is available for public inspection at City Hall. Questions may be directed to Elizabeth Hude at (517) 978-0206. Sarah Jarvis City Clerk 1 Deborah Stuart From: Inside 208 <donotreply@wordpress.com> Sent: Thursday, January 03, 2019 3:09 PM To: Deborah Stuart Subject: [New post] Unwrapping Lame Duck 2018 – What Happened? Follow Up Flag: Follow up Flag Status: Flagged Chris Hackbarth posted: " When the Legislature wrapped up the 2017-18 session in the morning hours of Friday, December 21st, most of the legislators, staff, and lobbyists had no idea that this lame duck session had set records for the amount of bill activity. When the House and " New post on Inside 208 Unwrapping Lame Duck 2018 – What Happened? by Chris Hackbarth When the Legislature wrapped up the 2017-18 session in the morning hours of Friday, December 21st, most of the legislators, staff, and lobbyists had no idea that this lame duck session had set records for the amount of bill activity. When the House and Senate adjourned that morning, following the final 22 hour session marathon, it was reported that nearly 400 bills had moved during the four weeks of lame duck session...more than had passed during the preceding 23 months of the term. The Governor signed 340 new public acts and vetoed 56 bills during this record-breaking period. Numerous pieces of legislation that were brought up before the year ended had potential impacts on local government and the League was extremely active from both a proactive and defensive standpoint. The League's State Affairs team tracked and engaged on nearly 100 separate bills during lame duck 2018. One of the biggest negotiating pieces of the lame duck session was the completion of the supplemental budget deal. This deal hinged upon finding a funding stream for brownfield site clean-ups and expanding recycling programs once it became clear that the Governor’s proposed solid waste tipping fee increase did not have the votes to pass. In the end, HB 4991 was amended to earmark a portion of the state’s income tax revenue for additional road funding and the newly created “Renew Michigan” fund. Renew Michigan will receive $69 million per year for brownfield projects and recycling planning and expansion grants, all of which will be available to local units of government. This bill also allocates more than $100 million for the next two years to the Michigan Transportation Fund. The income tax revenue earmarked in this bill was shifted away from the school aid fund earmark in an amount equal to what the school aid fund is expected to increase as a result of the recent Wayfair US Supreme Court decision that allows states to collect sales taxes from online purchases. 2 Once HB 4991 passed, that cleared the way for the budget supplemental, SB 601, to pass. This bill included spending items of more than $1.2 billion, about $380 million of which was General Fund revenues. The 14 page analysis of the budget bill identified a $100 million deposit in the state’s rainy day fund, $114 million in additional road spending for the current year (about $25 million of that amount directly to cities and villages), the aforementioned $69 million for the Renew Michigan program, about $20 million in PFAS mitigation spending, $20 million in broadband expansion funding for under-served communities, $52 million dedicated towards the new Soo Lock project (pending federal appropriation), $7.5 million targeted at emergency disaster relief support for U.P. communities to help meet match requirements following the 2018 flood damage, and more than $115 million in “enhancement” grants spread among projects all around the state. Numerous League members received specific spending support for projects in this section and throughout the rest of the budget bill. While overall appropriations for revenue sharing were not impacted by either the income tax earmark or this supplemental appropriation, SB 601 did include a change in boilerplate for statutory revenue sharing payments that will allow any community that missed the December 1, 2018 certification and reporting deadline to receive 90% of their missed December payment if they submit the required documentation by February 1, 2019. With Governor Snyder completing his review of each of these nearly 400 bills late last week, the following is an outline of the main bills that the League engaged on and what we expect to return to in the new term. Bills and/or language we initiated or negotiated that were signed by the Governor - ∑ HB 6348 – The Personal Property Tax reimbursement formula. Now PA 616 of 2018, the bill creates a new mechanism to fully fund fire protection grants to more than 30 League member communities for the first time ever. The bill also accelerates the implementation of the next phase of the PPT reimbursement process to allow communities to start seeing their reimbursements reflect their current economic conditions and industrial investments, as opposed to their reimbursements being based on what their industrial tax base looked like in 2012. ∑ SB 838 – Expansion of pension and OPEB bonding authority for local units. Now PA 575 of 2018, this bill will allow single-A rated communities access to bond financing as tool to manage unfunded pension or OPEB liabilities. The law had previously been reserved for use only to those rated AA and above. ∑ HB 6049 – State Treasurer’s assessing reform proposal. Now PA 659 of 2018, the final product was modified significantly based upon our lobbying efforts and the input of local officials. Local government groups, including the League supported the compromise version and we were able to secure a huge concession that now will allow villages located in more than one township the option to consolidate their assessing duties under one assessor of record that they choose. ∑ HBs 5939-5941 – Enhanced local regulation of fireworks. Now known as Public Acts 633-635 of 2018, these changes to the state's fireworks law produced major concessions from the fireworks 3 industry, shrinking the number of days and the hours within those days that fireworks can legally be used. The new changes also offer local governments the ability to assess stiffer penalties for violations and additional regulations on temporary structures in some higher population communities. ∑ HB 6582 – Ballot FOIA reforms. PA 523 of 2018 was a priority for the League following the huge outcry from local clerks and communities when an unidentified “Emily” placed FOIA requests in nearly every community around the state for copies of every ballot and related information from the 2016 election. We worked to negotiate language in the Freedom of Information Act that will require a requester to provide their full name and contact information and institute a time frame for the requester to respond back to the local unit of government after they have received a payment or deposit request or the request becomes void. ∑ SB 110 – Clarifying authority for communities to negotiate below market housing incentives with developers. Now PA 585 of 2018, this legislation is the culmination of more than two years worth of effort to clear up the concern that these types of negotiations with developers are allowed and do not violate the state’s Rent Control Act. ∑ HBs 6087-6088 – MI Infrastructure Bank clarification. The League worked with legislators and the state to pass what are now Public Acts 507 & 508 of 2018 to ensure that communities could legally utilize the state’s Infrastructure Bank program without violating the Municipal Finance Act. ∑ SBs 1222-1223 – Tax capture conflicts with new PPT law. Public Acts 480 & 481 of 2018 reconnect a hold harmless provision that had been missed for certain TIF districts that had been impacted by the recent changes in the state’s personal property tax laws. When the new PPT system was adopted in 2014, language that had held districts in Battle Creek and Detroit harmless from any negative impact on their debt-related captures from exempt equipment was inadvertently left out of the PPT law and had to be reestablished. This change will restore approximately $3 million in lost reimbursements for those communities. ∑ SB 1253 – Street conversions. PA 440 of 2018 clarifies authority for cities to turn one-way streets back into two-way streets. ∑ SB 1116 – New Transportation Economic Development Fund categorical. PA 473 of 2018 creates the statutory language needed to implement the new Transportation Economic Development Fund Category B Community Service Infrastructure Fund grant program for road projects in cities and villages with populations less than 11,000. The current year budget has allocated $3 million in grants for eligible cities and villages under this category. ∑ HB 6064 – Creates a Rural Development Fund. PA 423 of 2018 establishes this new fund within the MEDC/MI Strategic Fund to benefit economic development efforts in smaller communities around the state. The bill allows for communities of less than 15,000 population to now access Community Revitalization Program grants for up to 50% of a project's eligible investment (maximum $10M) as opposed to the 25% maximum that normally exists for single project investments under the CRP. A new Rural Jobs and Capital Investment Fund is also created within the MSF that will have access, upon appropriation, to no more than $30 million to invest in eligible companies/economic development projects located in counties with less than 225,000 population. 4 ∑ SB 995 – Wetland Mitigation Board. PA 471 of 2018 provides for an increase in available funding and a needed clarification to the local agency wetland mitigation board. The bill provides changes that the League had sought to the fund program board make-up related to League-member participation and improved access to funding from this program. ∑ Bills where we secured language to protect local governments from potential negative consequences - ∑ SB 1235 – Bill to amend PA 33 public safety special assessments. Now PA 484 of 2018, the bill as originally introduced would have jeopardized access to this critical municipal finance tool and potentially every existing PA 33 special assessment in the state. we negotiated language to narrow the scope of the changes to simply clarify existing law and walk the sponsor back from gutting the law entirely. ∑ HB 6400 – Adult foster care facilities. PA 513 of 2018 amends the Zoning Enabling Act relative to adult foster care facilities. The League secured language in the new act that tightens the exemption from zoning for these types of facilities to ensure that a loophole was not created for uses outside of those receiving foster care benefits. ∑ HB 5098 – Utility/telecom line relocation. The League had originally opposed this bill, which is now PA 565 of 2018, based upon the negative impact it would have had on local control of rights of way. After sitting on the House floor for nearly a year due to strong local government opposition, the bill's proponents compromised on a lesser reporting change, removing offending language that would have gutted local oversight, permitting, and fees. Bill now simply clarifies project information sharing and reporting. Bills the League opposed that were not completed and the bills died - ∑ SB 329 & HB 4503 – Preemption of local zoning for "short-term" rentals ∑ SB 1188 – Preemption of all local vegetation/tree ordinances ∑ SB 927 – Rental Heavy Equipment PPT exemption without reimbursement ∑ SB 1031 – Full PPT exemption for all utility distribution equipment ∑ SB 1035 – Property tax exemption for certain sportsman/gun clubs ∑ SB 796 – Prohibition on any paid union release time ∑ SB 1260 – Requirement that all public labor unions re-certify every two-years ∑ HB 5898 – Gov Snyder's proposed water user fee ∑ SB 943 – Gov Snyder's proposed solid waste tipping fee increase ∑ SB 741 – Preemption of local dog breed ordinances ∑ SB 157 & HB 5723 – Preemption of local water & sewer system materials design specifications in favor of PVC materials ∑ SBs 626-627 – Preemption of local sea plane ordinances ∑ SB 924 – Proposal to authorize private police forces 5 ∑ HB 4968 – Proposed changes to conflict of interest standards for planning commission members ∑ HB 5916-5917 – Preempts local pet shop ordinances related to puppy sales/puppy mills - these bills were vetoed by the Governor ∑ SB 964 – Bill would broaden access to digital billboards, change permit and fee structures, and requirements for public notice for clearing vegetation - bill was vetoed by the Governor Bills the League supported that didn’t make it through the process – ∑ HB 4985-4986 – Switching disabled veteran property tax exemption from a local exemption to a state income tax credit ∑ SB 1209 – Legislation to reverse recent court decision that undermines the state’s hard cap/80-20 health insurance cost-sharing law ∑ SB 756 – Clarifying local government’s ability to create Storm Water Authorities in compliance with the Supreme Court's Bolt decision ∑ HB 4290 – Provide additional liability protection for local governments from basement back-ups during storm events ∑ HB 5385 – Correct problem with speed limit setting for cities and villages in residential areas ∑ SB 469 – Re-establish the state’s Historic Tax Credit program to complement the federal historic tax credit ∑ HB 5680 – Address concerns with tax status of residential solar equipment, treating those components as part of the home, similar to replacing a furnace or water heater ∑ HB 5325 & 5720 – Provide additional flexibility for Principal Shopping Districts and Business Improvement Districts to include residential properties within those districts in their assessment plans Bills the League opposed that became law – ∑ HB 6063 – Now PA 506 of 2018, this bill preempts local sign ordinances relative to flags or banners for military/first responders ∑ HBs 5955-5965 – Public Acts 493-503 of 2018 were a package of bills that preempt local occupational licensing and regulation programs, especially related to local licensing of occupations where the state already requires a license While this lame duck produced a number of victories for local governments, we expect many of the items that did not make it through the process to be brought back in the new legislative term. We will be prepared to continue engaging with League members to support or oppose those issues as appropriate in the coming months. 6 The 100th Legislature is scheduled to convene for the 2019-2020 session on Wednesday, January 9, 2019, but legislative action will likely not truly begin for a few weeks as we wait for new bills to be introduced and for House and Senate committee assignments and schedules to be announced. As always, if you have any questions on these bills or other policy issues, please contact the League's State Affairs team at 517-485-1314. Thank you to everyone for your support and engagement these past few weeks! Chris Hackbarth is the League’s director of state & federal affairs. He can be reached at 517-908- 0304 and chackbarth@mml.org. Chris Hackbarth | January 3, 2019 at 4:08 pm | Categories: Uncategorized | URL: https://wp.me/p3wSLH-1F6 Comment See all comments Unsubscribe to no longer receive posts from Inside 208. Change your email settings at Manage Subscriptions. Trouble clicking? Copy and paste this URL into your browser: http://blogs.mml.org/wp/inside208/2019/01/03/unwrapping-lame-duck-2018-what-happened/

City Manager ReportDecember 17, 2018City AdministratorPacket pages 65–67

Administrator’s Report

Source attribution: City Administrator Report during Deborah S. Stuart's tenure

Administrator’s Report: December 14, 2018 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to

Read extracted report text

Administrator’s Report: December 14, 2018 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to co-locate on the radio tower has been signed and a building permit has been issued. Anticipate installation of equipment to begin this winter. Pending Subdivisions: Enclave at Rayner Ponds (19 lots, 1 park) and Rayner Ponds – Phase 4 (16 lots) Subdivisions require three stages of approval before site plan approval and building permits can be issued – Tentative Preliminary Plat/Final Preliminary Plat/Final Plat. Current stage for both: The City has approved a Tentative Preliminary Plat for both projects (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Staff anticipates the applicant will submit a Final Preliminary Plat for Rayner Ponds – Phase 4 in December. 154 W. Maple (former shoe store) The Planning Commission approved the Final Site Plan on December 11 meeting. Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 118 W Oak Former school administration building Two applications received - one to re-zone the property to C1 Central Business District, the second for Final Site Plan approval for the use of the property as an entertainment venue with an escape room on the 2nd floor and arcade on the first floor. Staff is working with applicant to obtain complete information necessary for evaluating the proposal. OPERATIONS AND COMMUNITY RELATIONS • March 19-20, 2019 will be the MML- 2019 Capital Conference. Councilmembers please let Dana Martin know if wish to attend. • The City has been notified that we have received the following grants: o MDEQ - $3,225 for the well head protection program o DNR - Forestry Division $9,500 for tree evaluation • Mason staff recently participated in Shop with a Cop on December 1st and Ingham County TRIAD No Senior without Christmas on December 6th. • Two patrol officers traveled to Metro-Detroit for a 2-day Active Violence Training, sponsored and partially funded by MMRMA. Staffing Updates: • New Hires/Promotions: Jeremiah Budd and Joseph Fairbotham were sworn in as the new Police Sergeants on Monday, December 10. Beau Cornell was promoted to Equipment Operator on December 10. • Open Positions: Assistant Finance Director Interviews completed; staff making final selection. Utility Foreman (POTW) interview completed; staff making final selection. Police Officer position has been posted applications due by January 11, 2019. DPW Laborer position has been posted applications due by January 4, 2019. 65 LARGE PUBLIC PROJECTS FY 2018-2019 Project Project Name/Description Status Completed STREETS, SIDEWALKS, BRIDGES (S) 2017-S6 South St - Northbrook to City Limits Complete Sep 2017-S7 Avon Street - All Complete Sep 2017-S8 Northbrook - South to Carom Circle Complete Sep 2017-S9 S. Jefferson - Oak Street to Kipp Road Project has been let through the MDOT system. Rieth Riley is low bidder. 2017-S10 Sidewalk Program - Summerwood Documents prepared for a Jan advertisement and spring construction. 2018-S1 MDOT- Temple Street Safety Grant Project is funded for FY19 (Oct. 1- Sept. 30). Package to be submitted to MDOT. 2018-S32 Columbia - Cedar to US 127 Complete Sep MDOT – South Street Bridge Repair Complete Nov MDOT – Cedar/Ash intersection MDOT does not have a start date yet. MDOT – Steele Street signaled pedestrian crossing Complete Aug UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) 2018-U1 Utilities for Properties on Kipp Road Complete Sep 2017-U3.2 Waste Water Treatment Plant Upgrades Complete Oct 2017-U3.3 Design of the New DPW Facility After 2017-U3 2017-U6 Abandon Wells by Airport Project on hold; filed FAA permit to do work – up to 45-day response period. 2017-U9 Northbrook - South to Carom Circle Complete Sep 2017-U10 S. Jefferson - Oak St to Kipp Road See 2017-S9 2017-U12 300,000 G Storage Tank Top Sealing Delayed until next FY N/A 2017-U13 Well No. 7 Rebuild Well work is complete. The motor is on order. 2017-U15 Replace Two Fire Hydrants Behind Mason Plaza Work scheduled for spring construction 2017-U16 Cathodic Protection for Ground Storage Tank Planning stage. 2017-U17 High Service Pump No. 1 Rebuild In progress 2017-U18 Replace Chlorine Analyzer Complete Aug 2018-U35 BS&A Work Order Application Award of project anticipated in December to coordinate with other projects involving BS&A software. 2018-U36 Sewer Push Camera Replacement Complete Nov 2018-U37 Log Jam Removal Sycamore Creek Complete Nov PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) 2017-P8 Laylin Park Improvements Staff is evaluating final work priorities for the spring. 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) Complete Nov 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension Complete Nov 2018-P3 Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements In progress 2018-P5 City Tree Evaluation Bid packets announcement will go out December 16 Bid opening January 4 2019. 66 MOTOR VEHICLE POOL (MVP) 2017-MVP6 1/2 Ton 2x4 Pickup Truck Complete Sep 2017-MVP7 Mower Complete Jul 2017-MVP8 Police Cars On order 2017-MVP9 Large Items (Leaf Vacuum) Complete Nov 2017-MVP10 5-yard Dump/Plow Trucks Cab/Chassis (City Council consideration 12.14.18) 2017-MVP18 Command Vehicle Complete Oct 2017-MVP30 Front End Material Loader Complete Nov BUILDING, PROPERTY, EQUIPMENT (B) 2017-B1 Library- Facility Evaluation In progress 2017-B3.1 Police: Portable Radios Complete Oct 2017-B4 City Hall Landscaping and Lighting Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. 2017-B6 Fire: Fire Engine 809/Tower 808 Recommendation to City Council 2018-B4 IT: BS&A Timesheet Program Not started, connection issues with offsite facilities 2018-B4 IT: BS&A Cemetery and HR Upgrade Complete Nov 2018-B6 IT: AV Room Technology Patch Evaluation is complete; staff are reviewing 2018-B7 Planning: Cedar/127 Corridor (Transportation and Land Use) Drafting scope/RFP 2018-B24 City Hall Rental Space Furniture Replacement Not started, evaluation planned during winter 67

City Manager ReportDecember 3, 2018City AdministratorPacket page 3

Administrator’s Report

Source attribution: City Administrator Report during Deborah S. Stuart's tenure

Administrator’s Report (11/20/2018) - Stuart reminded everyone about the Ribbon cutting ceremony for Hayhoe River Walk Trail and Dart Foundation Trailhead to take place on November 28, 2018 at 11:00 a.m.

Read extracted report text

Administrator’s Report (11/20/2018) - Stuart reminded everyone about the Ribbon cutting ceremony for Hayhoe River Walk Trail and Dart Foundation Trailhead to take place on November 28, 2018 at 11:00 a.m.

City Manager ReportDecember 3, 2018City AdministratorPacket pages 34–36

Administrator’s Report

Source attribution: City Administrator Report during Deborah S. Stuart's tenure

Administrator’s Report: November 30, 2018 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Planning Commission approved the Final Site Plan at a Special Meeting on Tuesday, September 25. HDC approved Certificate of A

Read extracted report text

Administrator’s Report: November 30, 2018 ACTIVE PRIVATE PROJECTS STATUS UPDATES Project Name Status 318 W. Kipp - Klavon’s 228 W. Kipp - Klavon’s Building permit active for construction of new restaurant. 322 S. Jefferson Commercial Bank – Downtown Mason Building permit active for interior renovations; restore second entrance doors on Jefferson St.; replace door and add concrete pad at alley entrance. The HDC approved a Certificate of Appropriateness for doors on 9/17/18. 402 S. Jefferson (former Baja Grill) Planning Commission approved the Final Site Plan at a Special Meeting on Tuesday, September 25. HDC approved Certificate of Appropriateness for façade on 9/17/18. Bids were received on 10/5/18 and project is on track for grant authorization. 201 W. Ash City Hall The T-Mobile contract to co-locate on the radio tower has been signed and a building permit has been issued. Anticipate installation of equipment to begin this winter. Pending Subdivisions: Enclave at Rayner Ponds (19 lots, 1 park) and Rayner Ponds – Phase 4 (16 lots) Subdivisions require three stages of approval before site plan approval and building permits can be issued – Tentative Preliminary Plat/Final Preliminary Plat/Final Plat. Current stage for both: The City has approved a Tentative Preliminary Plat for both projects (Stage 1) and is waiting to receive an application for Final Preliminary Plat (Stage 2). Staff anticipates the applicant will submit a Final Preliminary Plat for Rayner Ponds – Phase 4 in December. 154 W. Maple (former shoe store) An application has been submitted for Final Site Plan Review and will be on the December 11 agenda of the Planning Commission. Staff is working with the applicant to develop a demolition/construction schedule and maintenance of traffic plan that will minimize impacts to traffic and businesses in the surrounding area. 600 Buhl St. Ingham Animal Shelter Building permit active for new construction. 118 W Oak Former school administration building Two applications received - one to re-zone the property to C1 Central Business District, the second for Final Site Plan approval for the use of the property as an entertainment venue with an escape room on the 2nd floor and arcade on the first floor. Staff is working with applicant to obtain complete information necessary for evaluating the proposal. OPERATIONS AND COMMUNITY RELATIONS • Department of Public Works will start early morning shift starting next week get an earlier start to plowing and salting of Mason’s streets. Staffing Updates: • Open Positions: Staff reviewing applications for the Assistant Finance Director position. Police Sergeant 2nd Interviews completed; staff making final selection. Equipment Operator (DPW) position posted internally until December 3rd. Utility Forman (POTW) position posted internally until December 5th. 34 LARGE PUBLIC PROJECTS FY 2018-2019 Project Project Name/Description Status Completed STREETS, SIDEWALKS, BRIDGES (S) 2017-S6 South St - Northbrook to City Limits Complete Sep 2017-S7 Avon Street - All Complete Sep 2017-S8 Northbrook - South to Carom Circle Complete Sep 2017-S9 S. Jefferson - Oak Street to Kipp Road Project has been let through the MDOT system. Rieth Riley is low bidder. 2017-S10 Sidewalk Program - Summerwood Documents prepared for a Jan advertisement and spring construction. 2018-S1 MDOT- Temple Street Safety Grant Project is funded for FY19 (Oct. 1- Sept. 30). Package to be submitted to MDOT week of Sept 24. 2018-S32 Columbia - Cedar to US 127 Complete Sep MDOT – South Street Bridge Repair Complete Nov MDOT – Cedar/Ash intersection MDOT does not have a start date yet. MDOT – Steele Street signaled pedestrian crossing Complete Aug UTILITIES: SANITARY SEWER, STORM WATER, AND WATER DISTRIBUTION (U) 2018-U1 Utilities for Properties on Kipp Road Complete Sep 2017-U3.2 Waste Water Treatment Plant Upgrades Complete Oct 2017-U3.3 Design of the New DPW Facility After 2017-U3 2017-U6 Abandon Wells by Airport Project on hold; filed FAA permit to do work – up to 45-day response period. 2017-U9 Northbrook - South to Carom Circle Complete Sep 2017-U10 S. Jefferson - Oak St to Kipp Road See 2017-S9 2017-U12 300,000 G Storage Tank Top Sealing Delayed until next FY N/A 2017-U13 Well No. 7 Rebuild Well work is complete. The motor is on order. 2017-U15 Replace Two Fire Hydrants Behind Mason Plaza Work scheduled for spring construction 2017-U16 Cathodic Protection for Ground Storage Tank Planning stage. 2017-U17 High Service Pump No. 1 Rebuild In progress 2017-U18 Replace Chlorine Analyzer Complete Aug 2018-U35 BS&A Work Order Application Award of project anticipated in December to coordinate with other projects involving BS&A software. 2018-U36 Sewer Push Camera Replacement Complete Nov 2018-U37 Log Jam Removal Sycamore Creek Complete Nov PARKS/ CEMETERY/ FORESTRY/ NONMOTORIZED (P) 2017-P8 Laylin Park Improvements Staff is evaluating final work priorities for the spring. 2018-P1 Howell Road - Hayhoe Riverwalk (Dart Trailhead) Complete Nov 2018-P2 Howell Road - Hayhoe Riverwalk Trail Extension Complete Nov 2018-P3 Planning: 5 yr Parks/Recreation Plan; Bond Park Improvements In progress 2018-P5 City Tree Evaluation Preparing Bids and grant application is submitted 35 MOTOR VEHICLE POOL (MVP) 2017-MVP6 1/2 Ton 2x4 Pickup Truck Complete Sep 2017-MVP7 Mower Complete Jul 2017-MVP8 Police Cars On order 2017-MVP9 Large Items (Leaf Vacuum) Complete Nov 2017-MVP10 5-yard Dump/Plow Trucks Reviewing quotes 2017-MVP18 Command Vehicle Complete Oct 2017-MVP30 Front End Material Loader Complete Nov BUILDING, PROPERTY, EQUIPMENT (B) 2017-B1 Library- Facility Evaluation In progress. A community meeting was held on Thurs, Nov 8 to receive input. 2017-B3.1 Police: Portable Radios Complete Oct 2017-B4 City Hall Landscaping and Lighting Phase 1 completed. Phase 2/3 scheduled for the spring as time and budget allows. 2017-B6 Fire: Fire Engine 809/Tower 808 Recommendation to City Council 2018-B4 IT: BS&A Timesheet Program Not started, connection issues with offsite facilities 2018-B4 IT: BS&A Cemetery and HR Upgrade Complete Nov 2018-B6 IT: AV Room Technology Patch Evaluation is complete; staff are reviewing 2018-B7 Planning: Cedar/127 Corridor (Transportation and Land Use) Drafting scope/RFP 2018-B24 City Hall Rental Space Furniture Replacement Not started, evaluation planned during winter 36